Waitaki District Council logo Waitaki District Council

NATURALLY BETTER

 
Services A-Z

NOTIFIED RESOURCE CONSENTS

Notified Resource Consents

 

Main Planning page is here.


 

 Submission Form - Use this form to make a submission on a resource consent

 


 

Saleyards Road Private Plan Change information can be found here - Variation 6 Private Plan change.

Application Details

Application Summary

Dates

HOLCIM

Oamaru

LRC07/08

 

 

  Notice of Application for Submission

 

  Appn for Resource Consent - Cement Plant Site

  Appn for Resource Consent - Ngapara Coal Pit Site

  Appn for Resource Consent - Weston Quarries

  Appn for Resource Consent - Windsor

Holcim (New Zealand) Limited proposes to construct and operate a cement manufacturing plant on land owned by Holcim adjacent to the Weston-Ngapara Road, approximately 3 kilometres from the township of Weston and 7 kilometres west of Oamaru.

The proposed cement manufacturing plant and associated facilities, including storage silos, a raw material storage hall, rail loading facilities and offices/staff facilities, would have a total footprint of between 30 - 40 hectares.

The proposed cement manufacturing plant would use dry process technology which involves the drying and grinding of raw materials into a fine dry powder that is then fed to the kiln system.  The cement manufacturing plant is proposed to operate 24 hours per day, 7 days per week.  Used oil is also proposed to be stored at the cement manufacturing plant site, which would be used to supplement coal as a fuel for the kiln.

The main raw materials required to produce cement are proposed to be extracted from a quarry containing limestone and siltstone, and a quarry containing tuff, both in close proximity to the proposed cement manufacturing plant. The quarries are proposed to operate up to 12 hours per day, up to 6 days per week.  The limestone/siltstone and the tuff would be quarried using bulldozers with ripper attachments. The quarried material would be transported to the adjacent cement manufacturing plant by a belt conveyor system, within the quarry.  

Some of the quarried materials would be screened and crushed at a crusher to be located by the limestone/siltstone quarry at the beginning of the belt conveyor system.

In addition, silica sand would be obtained from a pit near Windsor. The pit is also proposed to operate up to 12 hours per day, up to 6 days per week. The sand would be excavated and then transported some 12 kilometres by truck to be stockpiled at the cement manufacturing plant site.

Lignite coal is proposed to be the primary fuel to run the cement manufacturing plant.  The coal is proposed to be extracted from a pit near Ngapara and again is proposed to operate up to 12 hours per day, up to 6 days per week.  The coal is proposed to be transported some 19 kilometres by truck to be stockpiled at the cement manufacturing plant site.

Other materials proposed to be used in the cement manufacturing plant site, such as used-oil and gypsum, would be delivered to the cement manufacturing plant by truck. The majority of the cement produced would be transported by rail to a port (Port of Timaru or Port Chalmers) for shipment, while trucks would be used to distribute cement south to southern local South Island markets

Submissions Closed:

19 June 2007

Holcim Final Decision

Appeals Closed:

29 February 2008


ENVIRONMENT COURT
APPEAL:

Appeal to Environment Court dismissed. The consent of the Waitaki District Council is confirmed. Now pending a decision from Holcim.






  Copyright ©2010 Waitaki District Council, All rights Reserved. Website design: Griffler Enterprises